Latest news
March 4, 2009
Notice to Proceed
May 26, 2009
Draft Reports SubmittedJune 29, 2010
Phase A Master Plan FinalizedNovember 5, 2010
Phase B Draft Conceptual Design Report SubmittedDecember 9, 2010
Final DFHAD SubmittedMarch 15, 2011
Final Phase B Conceptual Design Report SubmittedUseful links
Project Timeline
Project Kickoff Meeting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . March 4, 2009
Launch Project Website . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . March 13, 2009
Hydrology Update . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . April 14, 2009
Project Sponsor Hydrology Approval . . . . . . . . . . . . . . . . . . . . . . . . April 29, 2009
Draft Phase A Major Drainageway Planning Report . . . . . . . . . . . . . . May 26, 2009
Draft Flood Hazard Delineation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . May 26, 2009
Project Sponsor Comments Due . . . . . . . . . . . . . . . . . . . . . . . . . . . June 23, 2009
Final Phase A Major Drainageway Planning Report. . . . . . . . . . . . August 18, 2009
Final Flood Hazard Area Delineation. . . . . . . . . . . . . . . . . . . . . . . August 18, 2009
Preferred Alternative Plan Selected. . . . . . . . . . . . . . . . . . . . . . . October 13, 2009
Draft Phase B Major Drainageway Planning Report . . . . . . . . . . . December 8, 2009
Project Sponsor Comments Due . . . . . . . . . . . . . . . . . . . . . . . . . . March 13, 2010
Final Phase B Major Drainageway Planning Report . . . . . . . . . . . . . March 13, 2010
A Basin Area Map is Located HERE
Copyright © J3 Engineering Consultants